The Building Safety Act 2022 introduced a mandatory approval process for all Higher-Risk Buildings (18m+ or 7+ storeys): the Gateway 2 application. Before any construction work begins, the Building Safety Regulator (BSR) must approve the design and confirm the dutyholder arrangements are in place.

BSR can take up to 12 weeks to review a submission (and request further information, starting the clock again). A rejected or queried submission can delay your programme by months.

So what does BSR actually look for? Based on BSA 2022, the Building Safety Regulations 2023, and BSR published guidance, here is a practical breakdown of the six areas they assess — and where most submissions fall short.

1. Dutyholder appointments and competence evidence

The first thing BSR checks is whether the correct dutyholder structure is in place: Client, Principal Designer (PD), and Principal Contractor (PC). This is not the same as CDM 2015 dutyholders — BSA 2022 created separate, building-safety-specific roles with different competence requirements.

BSR requires evidence that:

Common rejection reason: Competence evidence is generic (a list of qualifications) rather than specific to BSA 2022 dutyholder responsibilities. BSR wants to see evidence that the PD understands building safety management, not just design competence.

2. The design documents — fire and structural safety

The technical core of the submission. BSR reviews the design against Approved Document B (fire safety), Approved Document A (structure), and the building-specific fire strategy.

Key documents typically required:

Common rejection reason: The fire strategy was written for planning (a high-level document) rather than Building Regulations. BSR needs a design-stage fire strategy with specific detail on evacuation, firefighting access, and system design — not a planning fire statement.

3. Change control arrangements

One of the most misunderstood Gateway 2 requirements. BSA 2022 Section 36 requires that before work starts, a change control process is agreed and documented — covering how design changes will be assessed, approved, and notified to BSR.

Not all changes require BSR notification — only Major Changes (defined in regulation) trigger a formal notification. But the submission needs to demonstrate that a system is in place to identify whether a proposed change is major or not.

BSR looks for:

4. Golden Thread — initial digital record structure

The Golden Thread of information is a continuous digital record of the building from design through construction and into occupation. Gateway 2 does not require a completed Golden Thread — but BSR expects to see that the structure and format have been planned and that the PC has committed to maintaining it during construction.

BSR typically wants to see:

Common rejection reason: The Golden Thread plan is an appendix with a list of document types but no commitment to a specific system, no nominated information manager, and no plan for as-built capture. BSR treats this as a high-risk gap.

5. Mandatory occurrence reporting arrangements

Under Regulation 37 of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, the PC must notify BSR of certain events during construction: structural failure or damage, fire spread beyond the compartment of origin, failure of a safety-critical system, and near misses that could indicate a systemic issue.

BSR expects the submission to include a brief explanation of how these obligations will be managed: who is the nominated person to identify and report occurrences, what the decision tree looks like, and how it will be communicated to the site team.

6. Signed declarations from all dutyholders

Finally, BSR requires signed declarations from the Client, Principal Designer, and Principal Contractor confirming they accept their BSA 2022 duties. These must be on the correct BSR form (not a generic declaration) and must be signed by a person with actual authority within the organisation.

Common issue: declarations signed by a project manager rather than a director or authorised signatory. BSR returns these and asks for re-execution.

What happens if BSR rejects or queries your submission?

BSR issues a Further Information (FI) notice setting out what is missing or inadequate. You then have a specified period to respond. The 12-week clock restarts from when BSR receives a complete response.

On complex buildings, it is not unusual for a submission to go through two or three rounds of FI notices. Each round can add 8–12 weeks to your pre-construction programme.

A pre-submission review identifies these gaps before the submission goes in — allowing the team to address them without programme impact.

Get your Gateway 2 submission reviewed before it goes to BSR

Our desktop review checks your pack against BSR criteria and provides a written gap analysis. Fixed fee: £750 exc. VAT. Delivered in 5–7 working days.

Learn More & Order →